STRATEGY
Achieve planning permission for residential project.
FACTSHEET
0.4
Acres
Capital Stack
Bond
Team
Blackbee
Beauchamps
Mathesons
Location
Drumcondra
Date Acquired
January 2020
GALLERY
PROJECT UPDATES
FEB 2020
Architect selected to carry out planning application: MCA
Planning consultant selected: Thornton O’Connor
MAR 2020
Topographical survey complete by Hollis
Conservation architect consultant selected: Rob Goodbody IGS | LinkedIn
Landscape architect: Stephen Diamond & Associates
Pre-planning drawings now complete. Pre-planning meeting will be requested in c.4 weeks, following the completion of a daylight/sunlight analysis and initial landscape drawings. The intention is to submit a full application by end of June, however, this is subject the DCC being able to process an application under the Government restrictions or soon after they are lifted
Immediate COVID 19 impact: Minimal
Slower planning process.
AUG 2020
Pre planning meeting with DCC Aug 11, 2020. Positive feedback.
Design development continues.
Target planning application date: Late Oct - early Nov 2020.
Additional planning consultants:
Fire: TBC.
Structural: CMD Consult
Civil: Muir & Associates
NOV 2020
Pre planning meeting #2 with DCC Nov 25, 2020. Very positive feedback. Advised to submit planning as per presented plans.
FEB 2021
Planning Application Submitted: Feb 9, 2021. Key dates:
Public consultation period ends: 15th March 2021
Decision date: 5th April 2021
APR 2021
April 1: DCC planning application received: Refused PDF
Drumcondra & Dublin Planning | Newstalk Breakfast | April 22, 2021
Drumcondra & Dublin Planning | Claire Byrne RTE Radio 1 | April 22, 2021
April 28: First party appeal submitted to ABP: PDF
AUG 2021
ABP decision delayed until Oct 25, 2021. ABP Letter | PDF
Existing planning permission extended to July 2024. DCC Letter | PDF
OCT 2021
ABP decision extended to an unspecified later date. Likely Q1 2022. ABP Letter PDF
NOV 2021
ABP approve nearby 1,592 unit BTR scheme Irish Times